Stage 3 Separation

Polymer drilling fluid recovery for the Gordie Howe International Bridge

  • Construction

BOS Environmental Solutions, now Stage 3 Separation, provided slurry management services for the Gordie Howe International Bridge Project, one of the longest bridges in North America.

Hydromill shaft-drilling equipment operating beside a fluid-treatment system

The Mission

Polymer drilling fluid used in the cased drilled-shaft process was recycled through the patented BOS tank process for reuse during construction of an international six-lane bridge spanning more than a mile and a half.

Hydromill shaft-drilling machine at an active construction site

Standard Project Pitfalls

Conventional settling tanks take days for solids to drop out, and over time the solids go colloidal and stop settling at all. The fluid gets heavier until it has to be disposed of. Settling also needs a much bigger footprint and segregated storage, which roughly doubles the polymer needed on the job.

The Objectives

  • Recycle and reuse polymer drilling fluid throughout the project, reducing drilling fluid consumption.
  • Reduce polymer fluid disposal costs by eliminating vacuum truck haul-off.
  • Reduce the project's carbon footprint by eliminating unnecessary vacuum truck disposal loads.
Hydromill shaft-drilling site with treatment equipment and fluid tanks

The Solution

S3S built a BOS Tank system with two large-bowl centrifuges and staffed it with one technician who ran the entire fluid system: removing drilled clays, sands and silts from the polymer, and mixing fresh polymer to spec. Polymer returning from a shaft was pumped to a holding tank, processed daily, and the clean recovered fluid pumped straight back to the shaft for reuse.

The Numbers

Every figure here comes from the Gordie Howe International Bridge project.

32Drilled shafts

Shafts 6 to 10 ft (2 to 3 m) in diameter and up to 120 ft (36 m) deep.

60,000 galPolymer fluid per shaft

Each shaft used roughly 60,000 gallons (230 m3) of polymer fluid, recovered and returned rather than replaced.

160,000 galKept from disposal every two weeks

Continued reuse of recycled polymer kept approximately 160,000 gallons (600 m3) out of disposal every two weeks.

The Process

Polymer fluid moved through a controlled reuse loop, from the shaft to the BOS system and back.

  1. 01

    Build the starting fluid

    About ten 18,000-gallon tanks of polymer fluid were built to specification to begin the project.

  2. 02

    Pump returns to holding

    As drilling began, polymer from the shafts was pumped to a holding tank, where solids processing began.

  3. 03

    Process the fluid daily

    S3S processed the polymer slurry daily, removing the solids so the client could reuse the same fluid for ongoing and concurrent shafts.

The Conclusion

The BOS tank system and onsite fluids management cut operating costs by reducing drilling fluid consumption and the disposal fees that come with it. Recycling and reusing the polymer saved time and cost, met the fluid management and rheology objectives, and took numerous trucks off public roads.